Performance measurement of turnarounds

Performance measurement of turnarounds
07 December

It is challenging to critically measure performance for shutdown, turnaround, and outages (STOs). However, it is a critical aspect of ensuring efficient and cost-effective operations. To successfully manage and track the progress of a STO event, key performance indicators (KPIs) serve as an early warning system, providing valuable insights into the project’s status and helping to prevent delays and cost overruns, increasing the overall event performance. 

A well-planned STO revolves around the concept of work packages. Work packages are detailed plans that break down the overall project into manageable segments and tasks, making it easier to monitor and report progress and measure performance. Here are some essential KPIs to measure and report during the event: 

1) Schedule Adherence:

The most fundamental KPI is tracking the actual progress against the planned schedule. Delays in one work package can have a cascading effect on the entire turnaround, so measuring schedule adherence is crucial. 

2) Budget Control:

Keeping a close eye on the budget is equally vital. Monitoring expenses within each work package helps identify any potential cost overruns early on and allows for corrective actions.

3) Resource Utilization:

Assess the allocation and utilization of manpower, equipment, and materials. This helps ensure that resources are being used efficiently and that no work package is under- or over-resourced.

4) Safety Compliance:

Safety is paramount in the process industry. KPIs related to safety incidents and adherence to safety protocols should be closely monitored throughout the TAR.

5) Quality Control:

Ensure that the work in each package is performed to the required quality standards. Tracking defects and rework can provide insights into the overall quality of the turnaround.

6) Work Package Progress:

Breakdown the turnaround into individual work packages and track the completion of each package. This granular view helps identify bottlenecks and areas where additional support may be required.

7) Inventory Management:

Monitor the use of spare parts and materials. Efficient inventory management can reduce costs and ensure that the necessary components are on hand when needed.

8) Risk Management:

Track identified risks and their mitigation plans. This KPI helps in identifying potential issues before they become major problems. 

Measuring progress during a turnaround using these KPIs provides real-time insights into the health of the project, allowing for quick decision-making and mitigating potential issues before they escalate. A well-planned STO event, built around the concept of work packages, coupled with a robust KPI monitoring system, is essential for ensuring continued productivity, safety, and profitability. 

Latest Posts

quality control and quality assurance

Differences between Quality Assurance and Quality Control

Discover the pivotal role of Quality Assurance (QA) and Quality Control (QC) in managing inspections during STO-events.

26 April

Why an STO software alone isn't the end-game solution

Why an STO software alone isn’t the end-game solution

A STO software alone doesn't always hold the key to solving problems. It's important to conduct a thorough analysis and identify ...

25 March

The essential role of a complete cost dataset for turnaround excellence

The essential role of a complete cost dataset for turnaround excellence

Executing a successful turnaround requires meticulous planning, budgeting, and scoping. Despite these difficulties, the use of a p...

12 March

How to maximize turnaround efficiency via integrated data management

How to Maximize Turnaround Efficiency Via Integrated Data Management

Integrated data management, supported by analytics and a commitment to continuous improvement, propels efficiency, collaboration, ...

19 February

Request Information